Dear Sandels Building Colleagues and Students,
Thank you for your patience and cooperation as we continue work in the Sandels Building.
Since my previous update, the following activities have taken place:
- Work in the Dean’s suite is expected to be complete today, Nov. 18, and is anticipated to be ready for re-occupancy next week.
- A proposal for the 4th-floor lab upgrades has been received. Construction is anticipated to begin immediately after the Thanksgiving holiday. We will seek to confine noise-generating construction activities during times when the building experiences lighter occupancy loads.
- The new fume hoods are due to arrive Tuesday, Nov. 22
- Repairs being performed by FSU Maintenance in response to the recent plumbing issues are expected to be complete next week. New finish flooring in the 2nd-floor kitchenette was installed this week, and wall base and repair of bathroom ceilings should be completed by early next week.
- Classroom support personnel will remove consoles and AV equipment from the classrooms on the 3rd and 4th floors by early next week in preparation for upcoming work. Classes in these spaces are being relocated through the spring semester.
- Construction documents for bathroom upgrades are expected to be completed soon after the Thanksgiving holiday.
If you have questions that have not been addressed in an update, on the Sandels Response website or in the FAQs, please email sandelsresponse@fsu.edu, and we will answer your individual questions to the best of our ability.
Best regards,
Jim Clark
Provost and Executive Vice President for Academic Affairs
Note: Messages submitted to sandelsresponse@fsu.edu may be subject to disclosure pursuant to Florida’s public records laws. To ensure the privacy and protection of your personal health information (PHI), please do not submit any PHI or private health details via this website or email.