The following has taken place since my last update:

  • Pricing for the work in the basement and the Dean’s suite envelope repair was received and revised to reflect newly issued contract terms. This work will begin once purchase order is received.
  • Pricing for the fourth-floor renovations is in progress. The construction team is working to expedite the project and remedy schedule constraints relating to the delivery of the new HVAC mechanical system controls.
  • The new air handling unit #6 for the fourth floor has arrived. Installation is being coordinated with the start of construction.
  • Selections pertaining to the final wall colors and the interior finishes for the corridor floors are in progress.
  • Facilities Maintenance is working to complete the wall, ceiling and floor repairs required due to the plumbing issue encountered last month prior to the upcoming prospective faculty visits.
  • A solution for emergency power is being finalized. This plan will enable the support of research equipment during a power outage.