Dear Sandels Building Colleagues and Students,
Thank you for your patience and cooperation as we continue work in the Sandels Building.
Since my previous update, the following activities have taken place:
- The bidding process for the work in the basement, the Dean’s suite, and fourth floor is in progress and proposals must be submitted by the close of business today, Sept. 23. A purchase order is expected to be issued for the work early next week.
- Installation of the new carpet on the second and third floors is complete pending a final inspection by the project manager.
- The new air handling unit #6 for the fourth floor has shipped. Installation is being coordinated with the contractor.
- Facilities is assessing work needed in the bathrooms, including accessibility accommodations. The design process will begin once the assessment is complete.
- Facilities is ensuring appropriate backup redundancies are in place as a part of preparations for possible hurricanes or severe weather.
If you have questions that have not been addressed in an update, on the Sandels Response website or in the FAQs, please email sandelsresponse@fsu.edu, and we will answer your individual questions to the best of our ability.
Best regards,
Jim Clark