July 22, 2022

Date
Email Subject
Update from Provost Jim Clark on Sandels Building

Dear Sandels Building Colleagues and Students,

As work progresses, I’d like to earnestly express my gratitude for your continued engagement.

Here are the latest updates on the project:

  • The construction manager has begun the reconstruction of the walls demolished during mold remediation.
  • The new carpet for Suite 207 has been received and installation is expected to be underway by today. The delivery of the remaining new carpet for the second floor is expected by early August.
  • All the new carpet for the fourth floor has been received and installation is expected to begin next week.
  • The final coordination for installation of the radon mitigation piping is ongoing. The construction manager and the radon mitigation contractor have been onsite conducting tests of the proposed coring location.
  • The necessary materials required to install the active soil depressurization devices have been received. Piping will commence installation the week of July 25.
  • As per discussions with the department, the new fume hoods and Air Handling Unit 6 (AHU) continue to track for delivery.
  • The construction documents for the HVAC modifications and related architectural work described in phase one have been completed and submitted for permitting by Facilities Campus Design.

If you have questions that have not been addressed in an update, on the Sandels Response website or in the FAQs, please email sandelsresponse@fsu.edu, and we will answer your individual questions to the best of our ability.

Best regards,

Jim Clark
Provost and Executive Vice President for Academic Affairs