June 17, 2022

Date
Email Subject
Update from Provost Jim Clark on Sandels Building

Dear Sandels Building Colleagues and Students,

I’m pleased to report on our progress as we continue to address concerns regarding the Sandels Building.

Since my last update, the following activities have taken place:

  • Facilities administration has approved the design for Air Handling Unit 6. A requisition and purchase order are currently being reviewed and awaiting final approval from Facilities administration.
  • The fume hood vendor was on site June 14 to verify measurements of existing conditions and to ensure new conditions and equipment fit.
  • In the basement, mold remediation of the mats is complete, and the floor tile mastic has been removed. Testing has been performed, and results show clearances have been achieved.
  • New carpet is being priced for all floors. The selected product is compliant with FSU standards and features expedited shipping options to facilitate timely project completion.

If you have questions that have not been addressed in one of my updates, on the Sandels Response website or in the FAQs, please email sandelsresponse@fsu.edu, and we will answer your individual questions to the best of our ability.

Best regards,

Jim Clark
Provost and Executive Vice President for Academic Affairs